WHAT IS PIPES FOR FREMANTLE?

We are renewing the ageing water pipes and drainage networks in Fremantle's CBD. This work is essential in order to future proof the areas water supply, increase the stormwater capacity in the area, and reduce the risk of flooding.

To sign up for weekly project email updates, click here.

CONSTRUCTION SCHEDULE

Street

Estimated timing

High Street – Henry to Market Street

21 May to 5 July 2020

High Street – Henry to Roundhouse

24 June to 24 July 2020

Essex Street

27 July to 5 September 2020

Essex Lane

27 July to 5 September 2020

Leake and Cantonment St

27 July to 9 October 2020

Marine Terrace – Cliff to Essex

7 September to mid November 2020

Nairn Street

7 September to 9 October 2020

Norfolk Street

5 October to mid November 2020

Marine Terrace – Essex to Suffolk

29 September to 20 November 2020

High Street reinstatement
High Street closed from Wednesday 24 February to Friday 5 March 2021
22 February to 16 March 2021

Peter Hughes Drive - Fremantle Port Authority premises (Stage 1)

April to December 2020

Phillimore Street - Public Transport Authority premises (Stage 2A)

May to November 2021

Phillimore Street - Market to Pakenham (Stage 2B)

May to November 2021

27 July to December 2020

Cliff Street - railway line to E-Shed markets (Stage 3)

TBC
Cliff Street roundabout (Stage 4)
TBC

We will generally work between 7.00 am and 5.00 pm from Monday to Saturday.


MAP OF WORK IN FREMANTLE


DRAINAGE UPGRADE MAP

FREMANTLE WATER PERKS

To take part in Fremantle Water Perks to win monthly prizes and support businesses! Visit the dedicated webpage for more information.

POP UP SHOP - 66 HIGH STREET

The Pop Up Shop is open to the public on Tuesday and Thursday between 10am and 4pm. Drop in to speak to the Project Team about the project.

HOW TO USE THIS PAGE

Project updates can be found directly beneath this section. For specific information related to businesses, initiatives and Frequently Asked Questions, scroll to the very bottom of this page if viewing on mobile, or navigate through the column to the right of this page if viewing on desktop.




WHAT IS PIPES FOR FREMANTLE?

We are renewing the ageing water pipes and drainage networks in Fremantle's CBD. This work is essential in order to future proof the areas water supply, increase the stormwater capacity in the area, and reduce the risk of flooding.

To sign up for weekly project email updates, click here.

CONSTRUCTION SCHEDULE

Street

Estimated timing

High Street – Henry to Market Street

21 May to 5 July 2020

High Street – Henry to Roundhouse

24 June to 24 July 2020

Essex Street

27 July to 5 September 2020

Essex Lane

27 July to 5 September 2020

Leake and Cantonment St

27 July to 9 October 2020

Marine Terrace – Cliff to Essex

7 September to mid November 2020

Nairn Street

7 September to 9 October 2020

Norfolk Street

5 October to mid November 2020

Marine Terrace – Essex to Suffolk

29 September to 20 November 2020

High Street reinstatement
High Street closed from Wednesday 24 February to Friday 5 March 2021
22 February to 16 March 2021

Peter Hughes Drive - Fremantle Port Authority premises (Stage 1)

April to December 2020

Phillimore Street - Public Transport Authority premises (Stage 2A)

May to November 2021

Phillimore Street - Market to Pakenham (Stage 2B)

May to November 2021

27 July to December 2020

Cliff Street - railway line to E-Shed markets (Stage 3)

TBC
Cliff Street roundabout (Stage 4)
TBC

We will generally work between 7.00 am and 5.00 pm from Monday to Saturday.


MAP OF WORK IN FREMANTLE


DRAINAGE UPGRADE MAP

FREMANTLE WATER PERKS

To take part in Fremantle Water Perks to win monthly prizes and support businesses! Visit the dedicated webpage for more information.

POP UP SHOP - 66 HIGH STREET

The Pop Up Shop is open to the public on Tuesday and Thursday between 10am and 4pm. Drop in to speak to the Project Team about the project.

HOW TO USE THIS PAGE

Project updates can be found directly beneath this section. For specific information related to businesses, initiatives and Frequently Asked Questions, scroll to the very bottom of this page if viewing on mobile, or navigate through the column to the right of this page if viewing on desktop.




  • CLOSED: This survey has concluded.

    The Pipes for Fremantle project 2020 will be continuing the remaining works to replace existing pipes infrastructure across Fremantle. This work is essential in order to maintain our older water mains, and to avoid future bursts and leaks.

    This survey aims to understand what interested, impacted and concerned customers have to say, about the works in 2020.

    On the 2nd of December, we hosted an interactive workshop to get ideas and feedback from the community but are hoping to reach out via an online survey to get more feedback.

    This survey will close on the 20th December 2019 at 3pm.

    If you have any concerns or issues with completing this survey, please contact our customer solutions team on 9420 3529 or pipesforperth@watercorporation.com.au

    Take Survey
    Share on Facebook Share on Twitter Share on Linkedin Email this link
  • CLOSED: This survey has concluded.
    Take Survey
    Share on Facebook Share on Twitter Share on Linkedin Email this link