Upcoming work on Cantonment Street

12 Nov 2020

Cantonment Street from Market Street to Queen Street

Partially closed on 17, 20 & 24 November

Thank you for your patience and understanding as essential construction work in Fremantle to renew ageing water pipes and secure the area’s water supply for decades nears the end.

What is happening?

We will need to return to Cantonment Street to complete additional work near Market Street.

During this essential work, Cantonment Street from Market Street to Queen Street will be partially closed on Tuesday 17, Friday 20 and Tuesday 24 November from 7am to 5pm. Pedestrian management and detours will be in place.


How will this impact me?


Date 

Implications

Work duration

Tuesday 17 November


  • Cantonment Street from Market Street to Queen Street will be partially closed for preliminary service locate work.
  • To minimise impact, only one lane will be closed at a time to allow for one-way traffic. During the northern lane closure, traffic will be able to travel from Cantonment Street to Market Street. Driveway and delivery access to Cantonment Street will be via Queen Street.
  • During the southern lane closure, traffic will be able to go from Market Street to Cantonment Street. Driveway and delivery access to Cantonment Street will be via Market Street.
  • Market Street lanes will not be impacted by this work.

7am to 5pm


Friday 20 November


  • Cantonment Street from Market Street to Queen Street will be partially closed for about an hour.
  • During this work only one lane along Cantonment Street will be closed at a time to allow for one-way traffic. Market Street traffic lanes will not be impacted by this work.
  • Work will then continue within the Cantonment Street verge and footpath near Market Street. Traffic will not be impacted however pedestrian management will be in place.

7am to 5pm

Monday 23 November

  • Work will progress within the Cantonment Street verge and footpath near Market Street. There will be no traffic impacts however pedestrian management will be in place.

7am to 5pm

Tuesday 24 November

  • During final brick pavement reinstatement work, Cantonment Street from Market Street to Queen Street will be partially closed.
  • One lane along Cantonment Street will remain open to allow for one-way traffic. During the northern lane closure, traffic will be able to travel from Cantonment Street to Market Street. Driveway and delivery access to Cantonment Street will be via Queen Street.
  • During the southern lane closure, traffic will be able to go from Market Street to Cantonment Street. Driveway and delivery access to Cantonment Street will be via Market Street. Market Street traffic lanes will not be impacted.
  • Final work will also take place in the Cantonment Street verge and footpath near Market Street. Pedestrian management will be in place.

7am to 5pm


We understand this essential work will impact nearby residents and businesses and apologise for the disruption. We will work closely with you to minimise disruption as much as possible.

Who to contact?

·   Pipes for Fremantle DM Civil Project Engineer Tessa McGrath on 0438 364 426. 

  • Water Corporation customer solutions team on 9420 3529.
  • To report a fault, emergency or security issue – 13 13 75 (available 24 hours).
  • To speak to someone in-person, pop in to our Pop Up information centre at 66 High Street on Tuesdays and Thursdays between 10am and 4pm. 

More information

Share on Facebook Share on Twitter Share on Linkedin Email this link
comment
Reply notification settings
Submitting your comment
Cancel
    <span class="translation_missing" title="translation missing: en.projects.forum_topics.show.load_comment_text">Load Comment Text</span>